The heat wave broke in mid-August and our energy levels went up along with a noticeable improvement in everyone’s spirits.

We’ve continued to re-evaluate what is possible with the remainder of the year, and have begun prioritizing.  The duplex topped the list, followed by finishing the root cellar so that we can move all of our tools and materials out of our makeshift tool tent.  The last thing we’d like to accomplish is put the finish coats of plaster and floor in the common house to keep the dust down this winter.

That said, the last few weeks we’ve almost solely focused on the duplex.  We’ve gotten better at stacking bales so that the corners are more square.  The key is not to stuff the spaces around the corner bales to tightly or it’ll push them out.  Apart from stacking the bales, stuffing the gaps, and trimming them we’ve also put in several electrical outlets connected to our off-grid grid.

To put the outlets in we nail the outlet boxes to plywood stakes, cut out space for the box in a bale with a chainsaw and then drive the stake/outlet box into the wall.  The electrical wire is just tucked in between the bales.

For the roof we installed two pieces of tarp as interior liner and used trim to secure it to the roof rafters.  Then we packed in scrap alpaca wool to fill in the space made by the liners and the 2×12 rafters.  We sprayed the wool with a borax solution to keep pests out and help with fire resistance, though wool is naturally fire retardant and straw bales coated in earthen plaster won’t burn.

 

 

Next, we put another tarp over the alpaca fiber to keep critters out of it and to act as secondary barrier like tar paper in case the metal roof ever leaks.  Lastly we put on the metal roof.  The only thing left to do on the roof is to put the gutters on.

Apart from putting in a couple more wine bottles in our walls to let more light in we’re ready to start plastering.  Earthen plastering is a very labor-intensive part of straw bale construction, though we generally find it to be satisfying work.  We hope those who joined our August 18th workshop felt the same way!  Luckily we’ve got a couple of new volunteers showing up early next week.  They’re well aware that we’ve got a bunch of plastering for them and so that should speed us along.

Our goal for the year is to get the base coat of plaster(it’s one of three coats) on the interior and exterior, and then to at least get the second coat or infill coat of plaster on the exterior, but hopefully the interior as well.  We’d like to build our rocket stoves before winter too, but we may have to make due with kerosene heaters if time doesn’t permit it.

The Drought

We managed to get all of 1/2″ of rain last weekend, and it looks like hurricane Isaac may deliver us some more hopefully.  The problem is that’s all the rain we’ve gotten this month.  Out average rainfall for August is typically 4.25″.  I have no idea what kind deficit we’re running for the year, but we may have gotten 2″ since the end of April. Even the wild trees are dying.  It seems contained to dogwoods and maples at the moment, although you can tell the oaks and other big trees are stressed too.

Apart from the tomatoes, peppers, and a few other plants we’ve essentially given up on the garden for the year.  You can’t win them all.

1st Annual Harvest Festival – September 29th

In other news, we’ll be holding our first ever harvest festival.  There will be a wine making workshop, archery, disc golf tournament, hiking, swimming(weather permitting), home-brew tasting, a potluck dinner, and camping. Everyone is invited, just please RSVP especially if you plan on camping and/or want to stay in one of our guest tents.

 

Window Bucks

We finished construction of the window bucks today.  We’re using small high-efficiency double-glaze low-e windows which we were able to score from a couple different places for $25/each.  I wish we’d used pre-built windows and doors in the common house.  Unfortunately, we’re not skilled enough carpenters yet to make doors and windows that seal well.

These bucks are known as floating bucks because they won’t be secured to the frame, but will simply rest on the bales and be held in place by compression.  We’ll put some screws on the outside of them so that they bite into the bales.

All that’s left is to stain and oil them.  Then we’ll be ready to start stacking bales!

July 2012 Newsletter: The Doldrums

The doldrums of June spread into July, but despite the incessant heat we soldiered forward on our projects.  We haven’t been accomplishing as much as we’d hope though, and have decided to postpone finishing the rainwater cistern until next year.

We’re still making good progress on the duplex.  Jesse has installed some bracing because the 2nd story was wobbly, and the bracing has really made a huge difference. He along with some volunteers also put in the blocking on the roof to fill in all the gaps between the purlins.

Over the last month we’ve finished the framing, dug the foundation drainage/insulation trench, put down the gravel bag stem wall, and poured the base layer of earthen floor.

We just finished placing the foam board insulation and drain tile in the rubble trench.  The foam board isn’t exactly environmentally friendly.  We’re thinking about using a layer of empty soda bottles as a dead air barrier in future construction.

Tomorrow we’ll fill it in with clean 1″ gravel and can move on to other building aspects like building window bucks, finishing the roof, and actually stacking the bales!

We finished installing the metal on the roof last week and we’ll have the gutters done tomorrow.  We used some semi-transparent pieces of roofing to let more light in and it looks they’re going to let in plenty of light.  We’ll probably only need a few lights inside.

We’ve done a good bit of digging in the root cellar squaring it up and getting it down to a better depth so some of us taller folks will be able to walk around in it without knocking our heads on the rafters.

There’s still part of a day of digging left to do on the root cellar, and then it’s on to framing it up, plastering the walls, and adding the gravel floor, shelves, and steps.

We had a wonderful 4th of July party, made some new friends and enjoyed the company of some old ones.  On the 21st we held an earthen floor workshop which was sparsely attended, but enjoyable and hopefully helpful nonetheless.  By the way, our next workshop is earthen plaster on August 18th!  Come by, learn something new, and give us a hand!

As it does every year about this time we’ve gone lax on our gardening duties as we fall behind on construction projects.  The drought certainly hasn’t helped anything, but despite that we’re still getting a nice crop of tomatoes.  So far the favorites are the yellow cherries and the hillbilly orange tomatoes. We also got a good haul of potatoes, onions, and garlic.

Most everything else is in serious need of water, but we’ve mainly kept the watering to a minimum and have been making sure the perennial fruit and berry bushes don’t die.

We’ll still plant a few more things for a fall garden, but unless the rain picks up we won’t expect much.  If we weren’t so pressed on construction we’d be hauling more water, ah priorities.  Next year we’ve got a full-time garden manager already signed up so that should help alleviate this seasonal decline.

We’ve had a number of comings and goings this last month, Dan, Lucy, Mike, Tristan, Tony, Bobbie, Janis, and Natalie.  We appreciate all of the hard work everyone has put in!